Add templates to a project from the Design Progress tab using the phase dropdown.

CDC Checklist 38 tasks
Week 1Phase 1 — Project Initiation 4
1.1Initial Client Consultation — confirm scope, brief & budget
1.2Survey + Title Search + Covenant review
1.310.7 Certificate (Planning Certificate)
1.4Confirm CDC pathway viability with Town Planner
Weeks 2–3Phase 2 — Concept Design 4
2.1Prepare Concept Design (plans, elevations, 3D)
2.2Cross-check with Zak to confirm project costing aligns with budget ⊙ Hold Point
2.3Showcase Concept Design to Client
2.4Obtain client sign-off on concept direction
Week 4Phase 3 — Consultant Engagement 9
3.1Consultant Issue — issue drawings to all consultants
3.2Civil / Driveway Design — engage civil engineer for crossover & levels ⚠ Authority · Critical Path
3.3S73 Design — Sewer & Water Tap-In design to Sydney Water ⚠ Authority · Critical Path
3.4Geotech Report
3.5Structural Engineering
3.6Stormwater / Hydraulic Engineering
3.7BASIX + NatHERS Assessment
3.8Landscape Plans
3.9Town Planner CDC compliance report
Weeks 5–6Phase 4 — Design Development & Coordination 6
4.1Review Consultant Drawings for clashes & compliance
4.2Finalise Architectural Coordination across all disciplines
4.3Prepare Architecture CDC Drawing Set
4.4Building Specifications
4.5Waste Management Plan (WMP)
4.6Design Verification Statement (DVS)
Weeks 7–8Phase 5–6 — Final Review, Sign-Off & Approvals 9
5.1Review Final Drawings — full internal QA check
5.2Cross-check final documentation with Zak ⊙ Hold Point
5.3Submit to Owners / Client for Final Confirmation
5.4Obtain written client approval to proceed
5.5Section 73 — Sydney Water Approval ⚠ Authority · Critical Path
5.6Sydney Water BDA Tap-In Approval ⚠ Authority · Critical Path
5.7Section 138/68 — Roads Act approval ⚠ Authority · Critical Path
5.9Certifier Forms completed
5.10Demolition Contractor Letter
Week 9Phase 7 — CDC Submission 6
7.1Submit full package to PCA (Private Certifier) for review
7.2Address any PCA review comments or RFIs
7.3Submit on NSW Planning Portal
7.4Track NSW Planning Portal uploads to completion
7.5Long Service Levy receipt obtained
7.6CDC Approved — certificate issued
DA Checklist 48 tasks
Week 1Phase 1 — Project Initiation 6
1.1Initial Client Consultation — confirm scope, brief & budget
1.2Survey + Title Search + Covenant review
1.310.7 Certificate (Planning Certificate)
1.4Confirm DA pathway viability — review LEP/DCP controls with Town Planner
1.5Identify if Pre-DA Meeting with Council is required ⚠ Authority · Critical Path
1.6Lodge Pre-DA application (if applicable) ⚠ Authority · Critical Path
Weeks 2–3Phase 2 — Concept Design 4
2.1Prepare Concept Design (plans, elevations, 3D)
2.2Cross-check with Zak to confirm project costing aligns with budget ⊙ Hold Point
2.3Showcase Concept Design to Client
2.4Obtain client sign-off on concept direction
Weeks 3–4Phase 3 — Pre-DA Response & Design Refinement 3
3.1Receive & review Pre-DA Meeting notes from Council ⚠ Authority · Critical Path
3.2Address any Council feedback — update design as required
3.3Confirm consultant requirements arising from Pre-DA feedback
Weeks 4–6Phase 4 — Consultant Engagement 14
4.1Consultant Issue — issue drawings to all consultants
4.2Civil / Driveway Design — engage civil engineer for crossover & levels ⚠ Authority · Critical Path
4.3S73 Design — Sewer & Water Tap-In design to Sydney Water ⚠ Authority · Critical Path
4.4Geotech Report
4.6Stormwater / Hydraulic Engineering
4.7BASIX + NatHERS Assessment
4.8Landscape Plans
4.9Arborist Report (if trees affected)
4.10Heritage Impact Statement (if heritage listed / HCA)
4.11Flood Assessment (if flood-affected land)
4.12Acoustic Report (if required by DCP / proximity to noise source)
4.13Traffic & Parking Assessment (if applicable)
4.14Shadow Diagrams — confirm compliance with LEP/DCP overshadowing controls
4.15View Analysis / Streetscape Perspective Montage (if required)
Weeks 6–8Phase 5 — Design Development & Coordination 7
5.1Review Consultant Drawings for clashes & compliance
5.2Finalise Architectural Coordination across all disciplines
5.3Prepare Architecture DA Drawing Set
5.4Building Specifications
5.5Waste Management Plan (WMP)
5.7Schedule of External Finishes & Materials
5.8Clause 4.6 Variation Request — prepare justification (if any non-compliance) ⚠ Authority · Critical Path
Weeks 8–9Phase 6 — SEE & Supporting Documentation 5
6.1Statement of Environmental Effects (SEE) — draft or engage planner
6.2Cost of Works Estimate (for DA fee calculation)
6.3Access Report / BCA Compliance Statement (if applicable)
6.4SEPP 65 Design Verification Statement (if 3+ storeys residential flat)
6.5Town Planner DA compliance review — confirm full package
Weeks 9–10Phase 7 — Final Review & Sign-Off 5
7.1Review Final Drawings — full internal QA check
7.2Cross-check final documentation with Zak ⊙ Hold Point
7.3Submit to Owners / Client for Final Confirmation
7.4Obtain written client approval to proceed with DA lodgement
7.5Long Service Levy receipt obtained
Week 10Phase 8 — DA Lodgement 4
8.1Lodge DA on NSW Planning Portal ⚠ Authority · Critical Path
8.2Upload all supporting documents & consultant reports to Portal
8.3Pay DA lodgement fees
8.4Confirm lodgement accepted — DA number issued ⚠ Authority · Critical Path
Construction Certificate Checklist 34 tasks
Week 1Phase 1 — PCA Engagement & CC Kick-Off 5
CC01Appoint Private Certifier (PCA)
CC02Receive CC Checklist from PCA
CC03Review DA Conditions of Consent — identify all pre-CC conditions
CC04Cross-reference PCA checklist against Conditions of Consent
CC05Confirm scope & programme with Zak ⊙ Hold Point
Weeks 1–6Phase 2 — Authority Approvals (Long Lead) 4
CC06Section 73 — Sydney Water Approval ⚠ Authority · Critical Path
CC07Sydney Water BPA — Building Plan Approval ⚠ Authority · Critical Path
CC08Section 138 — Roads Act approval (Council) ⚠ Authority · Critical Path
CC09Section 68 — Council infrastructure / activity approvals ⚠ Authority · Critical Path
Weeks 2–4Phase 3 — Consultant Reports & Certificates 8
CC10Structure design and certificate
CC11Stormwater design and certificate
CC12Geotech report
CC13Acoustic Compliance Certificate
CC14Aircraft Noise Assessment
CC15BASIX + NatHERS Certificate
CC16Erosion and sediment control plan
CC17Survey (updated if required)
Weeks 2–4Phase 4 — Architectural & Site Documentation 7
CC18Architecture set — CC issue drawings
CC19Building Specifications
CC20Driveway details
CC21Landscape plans
CC22Waste Management Plan (WMP)
CC23Construction Traffic Management Plan (CTMP)
CC24Dilapidation report
Weeks 3–5Phase 5 — Administrative, Fees & Forms 3
CC25Long Service Levy receipt obtained
CC26Receipt of all council fees
CC27Certifier Forms completed
Weeks 5–6Phase 6 — Final Review & CC Submission 7
CC28Cross-check all CC items satisfied with Zak ⊙ Hold Point
CC29NSW Planning Portal uploads — track all document uploads
CC30Submit full CC package to PCA for review
CC31Address any PCA review comments or RFIs
CC32Construction Certificate issued by PCA ⊙ Hold Point
CC33Notify Council of PCA appointment & CC issue
CC34CC Approved — ready for construction
Interior Design Checklist 33 tasks
Week 1Phase 1 — Engagement & Research 4
ID01Initial Client Consultation — understand design direction & material interests
ID02Request client inspiration & reference imagery
ID03Review project brief, spatial requirements & existing architectural plans
ID04Confirm room-by-room scope of interior design works
Weeks 2–3Phase 2 — Concept Design 3
ID05Develop material palettes per room
ID06Prepare initial concept sketches & mood boards
ID07Cross-check with Zak — confirm $$ and overall look & feel ⊙ Hold Point
Weeks 3–4Phase 3 — 3D Presentation & Client Approval 5
ID08Prepare floor plans & layouts for client presentation
ID09Prepare 3D models & renders for client presentation
ID10Present Concept Design to Client ⊙ Hold Point
ID11Obtain client sign-off on concept direction ⊙ Hold Point
ID12Incorporate all client feedback and update design accordingly
Weeks 5–6Phase 4 — Design Finalisation & Material Application 4
ID13Finalise material selections and specifications
ID14Commence interior design documentation with applied materials
ID15Coordinate AC location with services consultant
ID16Finalise Reflected Ceiling Plan (RCP) documentation
Weeks 6–7Phase 5 — 2D Documentation Preliminary 3
ID17Finishes Floor Plan — dimensions general rooms
ID18Internal Elevations — preliminary layout (no dimensions)
ID19Document 2D elevation design drawings
Weeks 7–8Phase 6 — 2D Documentation Second Stage 4
ID20Dimensions Plumbing (RED)
ID21Dimensions — kitchen, wet-areas, radius
ID22Dimensions — depth of all built-ins & bulkheads
ID23Cross-check all dimensions & ensure all relevant project information is added
Weeks 8–9Phase 7 — Electrical Layout 4
ID24Preparation of Electrical sketch & layout
ID25Downlights/Wall Lights & all GPO's etc.
ID26Dimensions — Lights & GPO
ID27Wiring diagram
Weeks 9–10Phase 8 — Final Review, Sign-Off & Issue 6
ID28Present to Zak — full internal QA check ⊙ Hold Point
ID29Resend final renders with Electrical overlay
ID30Add EL dimensions to 2D ID set
ID31Ensure all GPOs, Switches & Lighting are showing on plans
ID32Present to Client for final confirmation ⊙ Hold Point
ID33Finalise drawings for construction issue
Project Closure 2 tasks · actual date only
Project Closure 2
PC1Clean folder before pass it to past project
PC2Save archicad file as pla
Status
Project Name Address Project Owner Budget Consultant Fee Scope Delivery Priority Engagement Date
Project Outlook Active projects · all templates
📋
No project selected
Click + Project to create one, then select it above.
Weekly Priorities

Task swimlanes per team member — overdue and upcoming items.

Overdue
Due soon
Meetings

Meeting notes, action items and attendance records.

Pages
Select a meeting or create a new one.
Design Team
Consultants
Suppliers

Supplier directory, products and notes.

Pages
Financials

Track consultant fees against the project budget.

Design Review Checklist
Residential Pre-Submission
Overall progress0%